No.S/2017
21
Pusuc PRocuREMENT AND
DISPOSAL
oF Pusuc AssETs
Cap.22:23
Planning of procurement
(1) A procuring entity shall plan its procurement with a view to achieving
maximum value for public expenditure, so that the procurement is carried out within
available financial resources and other applicable limitations and at the most favourable
time.
(2) So far as possible, a procuring entity shall aggregate its procurement
requirements in order to achieve economies of scale and shall use framework agreements
where appropriate.
(3) Before commencing any procurement process, a procuring entity shall(a) investigate whether or not its requirements can be met internally, for
example by the transfer of goods from one department to another; and
(b) ensure that an accurate estimate has been prepared of the cost of the
procurement process, including the price of the procurement requirement
and the cost of contingencies that may reasonably be expected to arise
under the procurement contract; and
(c) ensure that the amount of the estimate referred to in paragraph (b) has
been properly covered in the entity's budget for the current financial year.
22
Annual procurement plan
(1) For each financial year and no later than one month after the end of such,
a procuring entity shall prepare a procurement plan which shall(a) be in accordance with a template prepared by the Authority; and
(b) contain at least such information as may be prescribed;
and shall forward the plan without delay to the Authority.
(2) The Authority and the procuring entity shall publish, in summary form, the
list of goods, construction works and services included in the entity's annual plan for
procurement during the coming financial year.
23
Individual procurement plan
( 1) In addition to its annual procurement plan prepared in terms of section 22,
a procuring entity shall prepare an individual procurement plan for each individual
procurement above the prescribed threshold value, which plan shall(a) be in accordance with a template prepared by the Authority; and
(b) contain at least such information as may be prescribed;
and shall forward the plan without delay to the Authority.
(2) The Authority shall publish on its website every plan forwarded to it in
terms of subsection (l).
24
Planning for shared procurement
Where two or more procuring entities conduct their procurement by way of shared
procurement arrangements in terms of section 19, the designated or lead procuring
entity, on behalf of the others, may prepare the plans referred to in sections 21,22 and
23, and for that purpose the other entities shall provide it with the necessary information
to enable it to prepare those plans and carry out the shared procurement activities.
25
Division of procurements
(1) Subject to this section, a procuring entity may divide a procurement
requirement, which could be procured in a single contract, into a package consisting of
58